How should a contractor payment schedule work?

Short answer

Each payment should be due when a defined piece of work is finished and you have looked at it, not on a calendar date. Keep the total paid a little behind the value of work done. California law says payments cannot exceed the value of work performed, and New York requires progress payments to bear a reasonable relationship to the work done.

The principle

Whoever is ahead on a construction job is the one taking the risk. If you have paid for more than has been built, you are lending the contractor money with nothing but a promise as security. If the contractor has built more than you have paid for, they are lending to you, with a lien right on your house as security. The second arrangement is the safer one for a homeowner, and a good schedule keeps you there by a modest margin throughout.

Arizona's Registrar of Contractors says it in eight words: do not allow payments to get ahead of the work.

What the law says in two states

California. There must be a detailed, written payment schedule in the contract, and payments to the contractor cannot exceed the value of the work performed, apart from the capped down payment.

New York. Any schedule of progress payments agreed in the contract must bear a "reasonable relationship" to the work done, materials purchased or other project-related costs.

Most states are silent after the deposit. Maryland's Home Improvement Commission notes that beyond the initial deposit its law does not control the payment schedule, and that payment terms can be negotiated between homeowner and contractor. So negotiate them.

Milestones, not dates

A schedule that says "25 percent on the 1st and 15th" pays for the passage of time. A contractor who falls behind gets paid anyway.

A schedule built on milestones pays for results. The Texas Attorney General describes how it should work: a partial payment schedule will usually specify what part of the job has been done when a partial payment is due, and you should inspect the work and make sure the contractor has met the schedule before you make your payment.

Good milestones are things you can verify without expertise:

  • demolition complete and debris removed
  • rough plumbing and electrical inspected and passed by the building inspector
  • drywall hung and taped
  • cabinets installed
  • final inspection passed

Milestones tied to inspections are the best kind, because someone other than you and the contractor has confirmed them.

A sample schedule

For a $40,000 kitchen in a state with a one-third deposit ceiling, a schedule might look like this. It is an illustration of structure, not a legal standard, and in California the first line would be capped at $1,000.

MilestonePaymentRunning total
Contract signed$4,000 (10%)10%
Cabinets ordered, supplier invoice shown$8,000 (20%)30%
Demolition and rough framing complete$6,000 (15%)45%
Rough plumbing and electrical pass inspection$6,000 (15%)60%
Drywall complete, cabinets installed$8,000 (20%)80%
Countertops, fixtures and flooring in$4,000 (10%)90%
Final inspection passed, punch list done, lien waivers received$4,000 (10%)100%

The last line is the important one. Holding back around a tenth until everything is truly finished is what makes the final details happen. More on that in final payment and the punch list.

Paying a milestone properly

  1. The contractor tells you the milestone is reached and sends an invoice referring to the contract line.
  2. You look. Walk the work with the contractor. For inspection milestones, see the inspector's sign-off.
  3. You collect lien waivers for the previous payment, and a conditional waiver for this one. California's board notes that by law you may withhold the next payment until you receive the unconditional releases for the previous one.
  4. You pay promptly. Within a few days. Paying on time when the work is done is your half of the bargain, and it keeps good contractors loyal to your job.
  5. You file the paperwork with the contract.

When the contractor asks for an advance

It will happen: a subcontractor wants paying, a delivery is due, payroll is Friday. One early payment will not sink you. A habit will.

If you agree, shrink it and document it. Pay the specific supplier invoice directly, or pay part of the next milestone against work that is visibly most of the way there. Put a line in writing that it is an advance on milestone five and not an extra.

Repeated requests for money ahead of work are the clearest early sign of a contractor in financial trouble. Check with the supplier, ask for lien waivers, and slow down.

Warning

If payments have got ahead of the work, stop paying until the work catches up. Say so in writing, calmly, with reference to the schedule in the contract.

Schedules when a lender or insurer is paying

On financed or insured work, somebody else may hold the checkbook. Ask how releases are approved and insist that your sign-off is required for each. The FTC mentions asking your bank or credit union about a certificate of completion that lets the bank pay the contractor stage by stage after disaster repairs. That is the same milestone idea with a bank officer in the loop.

Small jobs

A two-day job does not need seven milestones. A sensible version is a modest deposit for materials on the day work starts and the balance on completion, which is what Michigan's licensing department describes: a deposit when work begins, then scheduled payments as work progresses, and never the entire job in advance.

The contractor's standard schedule is 50 percent down and 50 percent on completion. Should I accept it?

In California, Maryland, Massachusetts and (over $5,000) Pennsylvania, half down exceeds the legal deposit limit. Elsewhere it is legal and puts you far ahead of the work on day one. Propose milestones.

Can I hold back more than 10 percent at the end?

You can negotiate any holdback the contractor will accept. It should be large enough that finishing is worth their while and small enough to be fair for work already done.

Sources

Sources last checked: November 2026. Written by the Before You Hire a Pro editorial desk. Report an error.